Index of Communications:


NAA Water Room Entrance Email (September 11, 2009)
NAA Water Emergency Room Entrance Email (September 9, 2009)
NAA Hot Water Outage Email (August 28, 2009)
NAA Hot Water Testing Email (August 21, 2009)
NAA Water Pressure Email (August 21, 2009)
NAA Hot Water Testing Email (August 13, 2009)
NAA Hot Water Email ( August 11, 2009)
NAA Hot Water Email NAW (August 11, 2009)
NAA Hot Water Email Update (updated August 7, 2009)
NAA Hot Water Project Schedule (updated August 5, 2009)
NAA Hot Water Project Schedule (updated August 4, 2009)
NAA Hot Water Project Schedule (updated August 3, 2009)
NAA Hot Water Project Schedule (August 1, 2009)
Work Locations and Schedule (updated July 1, 2009)
Work Locations and Schedule (updated June 26, 2009)
Work Locations and Schedule (updated June 24, 2009)
Work Locations and Schedule (updated June 22, 2009)
Work Locations and Schedule (updated June 18, 2009)
Work Locations and Schedule (updated June 16, 2009)
Work Locations and Schedule (updated June 15, 2009)
Work Locations and Schedule (updated June 12, 2009)
Work Locations and Schedule (updated June 10, 2009)
Work Locations and Schedule (updated June 9, 2009)
North Ave Projects Update Email - (June 5, 2009)
Work Locations and Schedule (updated June 3, 2009)
Work Locations and Schedule (updated June 1, 2009)
Work Locations and Schedule (updated May 30, 2009)
Work Locations and Schedule (updated May 28, 2009)
North Ave Projects Update Email - (May 27, 2009)
Work Locations and Schedule (updated May 20, 2009)
Davit Work Locations and Schedule (updated May 20, 2009)
North Ave Projects Update Email - (May 15, 2009)
Work Locations and Schedule (updated May 13, 2009)
Work Locations and Schedule (updated May 12, 2009)
North Ave Projects Update Email - (May 8, 2009)
North Ave Projects Update Email - (April 10, 2009)
Work Locations and Schedule (updated April 9, 2009)
North Ave Projects Update Email - (April 3, 2009)
Sealant Work Locations and Schedule (April 2, 2009)
Sealant Work Locations and Schedule (March 26, 2009)
Sealant Work Locations and Schedule (March 20, 2009)
North Ave Projects Update Email - (March 13, 2009)
Sealant Work Locations and Schedule (updated March 12, 2009)
North Ave Projects Update Email - (March 6, 2009)
North Ave Sealant Project Update Email - (March 6, 2009)
Sealant Work Locations and Schedule (updated March 6, 2009)
NAA Newsletter Issue VII - (March 2009)
Sealant Work Locations and Schedule (updated February 23, 2009)
North Ave Projects Update Email - (February 20, 2009)
North Ave Projects Update Email - (February 13, 2009)
North Ave Projects Update Email - (February 6, 2009)
NAA Newsletter Issue VI - (February 2009)
North Ave Projects Update Email - (January 30, 2009)
Brick Installation Progress (updated January 29, 2009)
Brick Installation Progress (updated January 27, 2009)
North Ave Projects Update Email - (January 23, 2009)
Brick Installation Progress (updated January 22, 2009)
North Ave Projects Update Email - (January 16, 2009)
Brick Installation Progress (updated January 13, 2009)
Brick Installation Progress (updated January 12, 2009)
North Ave Projects Update Email - (January 9, 2009)
Brick Installation Progress (updated January 7, 2009)
Brick Installation Progress (updated January 6, 2009)
NAA Newsletter Issue V - (January 2009)
Brick Installation Progress (updated December 31, 2008)
Brick Installation Progress (updated December 16, 2008)
North Ave Winter Break Update Email - (December 12, 2008)
Brick Installation Progress (updated December 5, 2008)
Brick Installation Progress (updated November 28, 2008)
North Ave Projects Update Email - (November 26, 2008)
North Ave Projects Update Email - (November 21, 2008)
Brick Installation Progress (updated November 19, 2008)
North Ave Construction Update Email - (November 14, 2008)
HVAC Female Room Entry Safety Protocol - (November 10, 2008)
North Ave Brick Replacement Update - (November 7, 2008)
North Ave Brick Removal Update Email - (October 31, 2008)
North Ave Brick Removal Update Email - (October 24, 2008)
NAA Newsletter Issue III - (October 15, 2008)
NAA Construction Work This Saturday Email - (October 10, 2008)
North Ave Brick Removal Update Email - (October 1, 2008)
North Ave Study Room Availability Email - (September 29, 2008)
NAA Newsletter Issue II - (September 17, 2008)
North Ave Brick Removal Update Email - (September 26, 2008)
North Ave Brick Removal Schedule and Website - (September 19, 2008)
North Ave No Trespassing Information - (August 22, 2008)
NAA Newsletter Issue I - (Handed out at Fall Check in)


Questions:

If you have questions, please contact your Hall Director

East Building
Vicky Dean
404-385-3239
vicky.dean@housing.gatech.edu
North Building
Nicole Morrison
404-385-3223
nicole.morrison@housing.gatech.edu
South Building
Jahsun Williams
404-385-3220
jahsun.williams@housing.gatech.edu
West Building
Joi Scales
404-385-7674
joi.scales@housing.gatech.edu